Recent and ongoing projects
Update of the RAP and socio-economic studies of Souapiti Dam
Client : Tractebel Engineering
Sectors: Energy | Infrastructure
Services: Social management | Studies
Client category: Consulting firms | Public institutions
Mission:
As a result of new elements related to the construction project of a hydroelectric dam in Souapiti, an update of the Environmental and Social Impact Assessment (ESIA) and the production of the Resettlement Action Plan (RAP) were required.
Results:
Insuco realized an update of the social baseline study, contributed to the Social and Environmental Management Plan, produced the RAP and the inventory of impacted asset and trees.
Tell us about your project!
Do you wish to discuss your project and its challenges? To learn more about Insuco and our expertise? To meet with us?