Update of the RAP and socio-economic studies of Souapiti Dam

Client : Tractebel Engineering

Region / Country: Africa | Guinea

Mission:

As a result of new elements related to the construction project of a hydroelectric dam in Souapiti, an update of the Environmental and Social Impact Assessment (ESIA) and the production of the Resettlement Action Plan (RAP) were required.

Results:

Insuco realized an update of the social baseline study, contributed to the Social and Environmental Management Plan, produced the RAP and the inventory of impacted asset and trees.